Flamanville-3 ranks #3 of 10 on Net electrical output of one currently operational reactor unit (MWe) (1,600 MWe); Saeul-2 ranks #9 (1,392 MWe).
Rank 03 of 10 · leads
Net electrical output of one currently operational reactor unit (MWe)
1,600 MWe
MakerEDF (EPR)
Date2024
Verified04 Sept 2026
Evidence
EDF Flamanville 3 site: EPR of about 1,600 MWe; the three-unit site page lists 2x1300 MW + 1x1600 MW. First grid connection 21 Dec 2024. EDF 14 Dec 2025: first time at 100% nuclear thermal power, 1,669 MW gross electrical. EDF still describes industrial commissioning tests as continuing in 2026 — included because it is grid-connected and has run at full thermal power, with that caveat here.Rank 09 of 10
Net electrical output of one currently operational reactor unit (MWe)
1,392 MWe
MakerKHNP (APR-1400)
Date2019
Verified04 Sept 2026
Evidence
IAEA PRIS Reactor Details, SAEUL-2, Operational, model APR-1400: Reference Unit Power 1392 MWe, Design Net 1340, Gross 1491, Thermal 3983 MWt. First grid 22 Apr 2019. 2024 history row uses 1392 MW (earlier years on the same page used 1418). Saeul-1 is the twin; its current live PRIS net was not loaded in this pass so it is not given a separate row.Try another pair
Source IAEA PRIS reactor-detail and country pages; EDF Flamanville 3 operator page